I've chosen Renzo Piano as reference to my major project. In this project, I will focus on 2 particular details which Renzo Piano did in IRCAM Extension building and the B&B Italia Offices. I am interested with the detail of the cladding in IRCAM Extension and the Roof detail of B&B Italia Offices. My aim for this project is to figure out how these 2 details are going to join together and work functionally. I would like to design a detail base on Renzo's detail however not imitating it. The cladding in the design is mainly to block some direct sunlight penetrate into the office. I am struggling on how the cladding is going to join with the columns, and how to stiffen a truss connection to the U Beam columns.... more to come
Wednesday, April 25, 2007
Tuesday, April 17, 2007
Construction Site: Reinforced Concrete Slab construction in Newcomb
Construction Site: Tilt Up Panel Construction in Newcomb
The proppings are screwed onto the concrete slab for a temporary brace stiffening. The line of slots on the bottom of the tilted up panels allow the concrete slabs to join up with the panels, allowing the panels to act as a structural component to support the whole building. When this is done, the propping will be removed.
This photo shows how a tilt up panel is being lift up by a crane.
I found out that the proppings are actually installed during the lifting panels take place.
This photo shows how a tilt up panel is being lift up by a crane.
I found out that the proppings are actually installed during the lifting panels take place.
The steel bars could be allowing other joinings to be installed sometime later during the construction. Also notice the small slots in between each panels, these slots actually allow steel plates wielded to join the tilt panels together.
Tilted up pannels supported by temporary proppings.